Channel Construction in Srengseng Urban Forest Reaches 30 Percent

Progress of 400-meter channel construction work in Srengseng Urban Forest Area (KHK), West Jakarta, which has been started since November 17, 2021 has now reached 30 percent. This project is targeted to be completed in April 2022.

The work has been carried out by 14 SDA Unit personnel since November 17, 2021

West Jakarta Water Resources (SDA) Sub-agency's Maintenance Section Coordinator, Lukman Hariadi mentioned that channel will be built with height of 2 meters and upper width of 150 centimeters. Later on, channels from residential areas will be connected with this channel and flow to Srengseng Urban Forest Reservoir.

"The work has been carried out by 14 SDA Unit personnel since November 17, 2021," he stated, Tuesday (1/11).

Koja SDA Unit Elevates Retaining Wall on Jalan Lorong 103

Channel construction was expected to overcome inundation that often occurs in the surrounding area during rainy season.

"Currently the progress has reached about more than 30 percent. If it goes well, it will be finished around April 2022," he explained.

Linked News
Popular News indeks
  1. Five Transjabodetabek Routes will Be Added to Tackle Traffic Congestion

    access_time09-05-2025 remove_red_eye667 personDessy Suciati
  2. Tanah Abang SDA Taskforce Normalizes Channels in Two Locations

    access_time12-05-2025 remove_red_eye444 personFolmer
  3. Munjirin Optimizes Physical and Non-Physical Development in East Jakarta

    access_time08-05-2025 remove_red_eye377 personNurito
  4. Community Work Held to Clean Environment in Petamburan

    access_time11-05-2025 remove_red_eye348 personFolmer
  5. Baduy Tribe Meets Pramono-Rano, Leaves Message of Protecting Nature

    access_time09-05-2025 remove_red_eye291 personDessy Suciati

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik